Question 575Steam Plants - Assistant Engineer
70% to passTo test an automatic low lube oil pressure trip on an idling turbo-generator and at the same time prevent the chance of bearing damage, you should _______________.
Aactuate the over speed trip, making a note at what pressure the oil is dumped from under the operating piston
Bsecure the steam supply valve to the throttle valve and observe the oil pressure as the throttle trips during the slowdown and ensure a supply of oil with the hand or standby pump when the pressure drops to 2-3 psi
Censure the standby lube oil pump, if so equipped, is properly lined up and set in the 'auto' mode, or the hand pump is being operated and then actuate the emergency trip
Dclose the generator steam throttle valve and then ensure a supply of oil through the hand or standby pump when the pressure drops to 5-6 psi
AI Explanation
The correct answer is B. To test an automatic low lube oil pressure trip on an idling turbo-generator and prevent bearing damage, you should secure the steam supply valve to the throttle valve and observe the oil pressure as the throttle trips during the slowdown. Ensure a supply of oil with the hand or standby pump when the pressure drops to 2-3 psi. This is the correct approach because it allows you to test the low lube oil pressure trip without risking bearing damage by completely shutting off the steam supply. The other options are either not directly related to testing the low lube oil pressure trip (A and C) or do not provide a sufficient oil supply when the pressure drops (D).
Related Questions
Q145:Which type of feed water regulator listed provides the MOST effective regulation... Q611:What type of lube oil cooler is shown in the illustration? Illustration GS-0122 ... Q233:What is the purpose of the movable air doors in an air register? Q721:For the gland seal regulator shown in the illustration, an increase in gland sea... Q87:After steam has been raised and a boiler is being placed on the line, the superh...
Ready to test your knowledge?
Take a Steam Plants - Assistant Engineer Practice ExamOfficial Resources