Question 87Steam Plants - Assistant Engineer
70% to passAfter steam has been raised and a boiler is being placed on the line, the superheater vent can be closed when _______________.
Athe boiler is supplying auxiliary steam
Bthe boiler steam stops have been warmed up
Cmain and auxiliary steam line drains are opened
Dboiler pressure is 5 psi above line pressure
AI Explanation
The correct answer is A) the boiler is supplying auxiliary steam. When a boiler is being placed on the line, the superheater vent can be closed once the boiler is supplying auxiliary steam. This allows the boiler to start heating the superheater coils and bring the superheated steam up to temperature before it is introduced into the main steam system. The other options are incorrect because: B) warming up the steam stops does not necessarily indicate the boiler is ready to supply steam; C) opening the drains does not mean the superheater vent can be closed; and D) 5 psi above line pressure is not the specific criterion for closing the superheater vent.
Related Questions
Q38:The leakage of air into the pump casing by way of the packing gland of a condens... Q77:Excessive carbon dioxide formed by improper chemical treatment in the boiler may... Q218:Boiler furnace brickwork can be fractured and broken by thermal shock caused by ... Q159:When preparing to light off a cold boiler equipped with a return flow fuel oil s... Q26:Oil accumulation in boiler water would _______________.
Ready to test your knowledge?
Take a Steam Plants - Assistant Engineer Practice ExamOfficial Resources