Question 3868 Deck General
70% to passA load line is assigned to a MODU to insure adequate stability and _______________.
A
structural strength
B
riser tension
C
mooring tension
D
lifesaving equipment
AI Explanation
You are correct, the answer A) structural strength is the correct answer. The purpose of a load line assigned to a Mobile Offshore Drilling Unit (MODU) is to ensure adequate stability and structural strength of the vessel. The load line is an important safety measure that helps prevent the MODU from being overloaded, which could compromise its stability and structural integrity. It is not related to riser tension, mooring tension, or lifesaving equipment, which are other important considerations for MODU operations, but are not the primary purpose of the load line assignment.
Related Questions
Q@q.QuestionNumber:The DEEP DRILLER, loaded as shown in the Sample Load Form #4 (Drilling), dischar...
Q@q.QuestionNumber:If your JP-5 barge has operated in salt water for less than 1 month in the 12 mo...
Q@q.QuestionNumber:When authorized to use chemical agents on an oil spill they would _____________...
Q@q.QuestionNumber:When the vessel is on coastwise articles, the original certificate of the seaman...
Q@q.QuestionNumber:During which condition should the operator of a pedestal crane shutdown operatio...
Ready to test your knowledge?
Take a Deck General Practice Exam
Official Resources
Want to practice with timed exams?
Download Coast Guard Exams for the full exam experience with progress tracking.
Get the App