Question 192Steam Plants - QMED
70% to passWhen performing a periodic gauge glass blow down to insure that the glass is free and operating correctly, what action is performed first?
AClose the bottom shut off valve and open the drain valve to clear out the bottom connection to the gauge glass.
BClose the top shut off valve and open the drain valve to clear out the bottom connection to the gauge glass.
CClose the bottom shut off valve and open the drain valve to clear out the top connection to the gauge glass.
DClose the top shut off valve and open the drain valve to clear out the top connection to the gauge glass.
AI Explanation
The correct answer is B) Close the top shut off valve and open the drain valve to clear out the bottom connection to the gauge glass. The reasoning for this is that when performing a periodic gauge glass blow down, the top shut off valve is closed first to isolate the gauge glass from the system pressure. This allows the bottom connection to the gauge glass to be cleared out by opening the drain valve, ensuring the glass is free and operating correctly. Closing the bottom valve first would not clear out the top connection, and closing the wrong valve entirely would not accomplish the intended purpose of the blow down. Therefore, option B is the correct procedure to follow.
Related Questions
Q91:Fuel oil settling tanks are used to _______________. Q12:The component shown in the illustration, labeled "IV", is the_______________. Il... Q145:While a vessel is underway, which of the conditions listed would indicate a leak... Q76:Which of the labeled items within the illustrated steam drum represents the last... Q165:The DC heater functions to _______________.