Question 192Steam Plants - QMED
70% to passWhen performing a periodic gauge glass blow down to insure that the glass is free and operating correctly, what action is performed first?
AClose the bottom shut off valve and open the drain valve to clear out the bottom connection to the gauge glass.
BClose the top shut off valve and open the drain valve to clear out the bottom connection to the gauge glass.
CClose the bottom shut off valve and open the drain valve to clear out the top connection to the gauge glass.
DClose the top shut off valve and open the drain valve to clear out the top connection to the gauge glass.
AI Explanation
The correct answer is B) Close the top shut off valve and open the drain valve to clear out the bottom connection to the gauge glass. The reasoning for this is that when performing a periodic gauge glass blow down, the top shut off valve is closed first to isolate the gauge glass from the system pressure. This allows the bottom connection to the gauge glass to be cleared out by opening the drain valve, ensuring the glass is free and operating correctly. Closing the bottom valve first would not clear out the top connection, and closing the wrong valve entirely would not accomplish the intended purpose of the blow down. Therefore, option B is the correct procedure to follow.
Related Questions
Q40:According to the illustrated lubricating oil system diagram, which of the labele... Q37:According to the illustrated lubricating oil system diagram, which of the labele... Q182:Excessive recirculation of condensate should be avoided, as it can cause _______... Q138:A lube oil sample is taken from the main engine lube oil system and visually ins... Q169:If the water level in a steaming boiler is dropping rapidly and cannot be kept a...