Question 41Steam Plants - 1st Asst/Chief
70% to passWhen preparing to hydrostatically test water-tube boilers, you should _______________.
Aremove all inspection plates and manhole covers as required by the marine inspector
Bmake arrangements for simultaneously testing main and auxiliary steam stops with water and steam pressure
Chave the boiler warmed to a temperature not exceeding 100°F
DD
AI Explanation
The correct answer is A) remove all inspection plates and manhole covers as required by the marine inspector. When preparing to hydrostatically test water-tube boilers, you should remove all inspection plates and manhole covers as required by the marine inspector. This allows the inspector to thoroughly inspect the interior of the boiler and ensure its integrity before the hydrostatic test is conducted. The other answer choices are incorrect because: B) is not necessary for the hydrostatic test itself, but may be required during other inspections. C) is not relevant, as the boiler should be at ambient temperature for the hydrostatic test.
Related Questions
Q400:Which of the following operational practices is helpful in avoiding the accumula... Q283:The solenoid valves in the fuel oil supply line to an automatically fired auxili... Q218:The boiler shown in the illustration would be classed as MO-0064 Q28:A single element boiler feed water regulating system used aboard ship utilizes _... Q16:Which of the listed systems would be a potential source for the high pressure dr...
Ready to test your knowledge?
Take a Steam Plants - 1st Asst/Chief Practice ExamOfficial Resources