Question 105Steam Plants - 1st Asst/Chief
70% to passWhen water washing a boiler, the proper sequence for washing the sections should be the _______________.
Agenerating tubes, superheater, and then economizer
Bscreen tubes, generating tubes, and then superheater
Csuperheater, economizer, and then generating tubes
Deconomizer, superheater, generating, and then screen tubes
AI Explanation
The correct answer is D) economizer, superheater, generating, and then screen tubes. The proper sequence for washing the sections of a boiler is to start with the economizer, then move to the superheater, followed by the generating tubes, and finally the screen tubes. This sequence ensures that the water flow effectively cleans the boiler from the least to the most critical components. The other options are incorrect because they do not follow the proper order. For example, option A starts with the generating tubes instead of the economizer, while option B skips the economizer entirely. Option C reverses the order of the economizer and superheater.
Related Questions
Q279:Which of the listed refractory materials can be used in an area directly exposed... Q206:The photoelectric cell installed as part of the combustion safety controls of an... Q72:Excessive carbon dioxide formed by improper chemical treatment in the boiler may... Q202:Fine adjustments to a boiler combustion control system, to bring about near perf... Q158:Dirty generating tube surfaces may cause higher than normal superheater outlet ...
Ready to test your knowledge?
Take a Steam Plants - 1st Asst/Chief Practice ExamOfficial Resources