Question 438Steam Plants - Assistant Engineer

70% to pass

Which procedure should be followed to dry out the fireside of a boiler after water washing?

APlace trays of silica gel in the furnace.
BUse a wire reinforced steam hose to put superheated steam in the furnace for 6 hours.
CAlternately fire one burner for 15 minute intervals during a 5 hour period.
DOpen the furnace registers and run the forced draft fans for 3 hours.
AI Explanation

The correct answer is C) Alternately fire one burner for 15 minute intervals during a 5 hour period. This is the correct procedure to dry out the fireside of a boiler after water washing. Alternately firing one burner for short intervals helps to gradually and evenly dry out the surfaces inside the furnace, preventing any sudden temperature changes that could damage the boiler. The 5 hour time period ensures the fireside is thoroughly dried before returning the boiler to normal operation. The other options are incorrect because: A) using silica gel is not an effective way to dry out a boiler furnace, B) using superheated steam could potentially damage the boiler, and D) simply running the fans without controlled firing would not properly dry the surfaces.

Want to practice with timed exams?

Download Coast Guard Exams for the full exam experience.

Get the App