Question 365Steam Plants - Assistant Engineer
70% to passA water-tube boiler can be laid up either wet or dry. If it is to be laid up wet, you should _______________.
Acompletely fill the boiler with deaerated feed water and maintain a slight pressure
Bdrain and refill the boiler when the pH goes above 6
Cdrain and refill the boiler each week
Dcompletely fill the boiler with water, then blow down to steaming level
AI Explanation
The correct answer is A) completely fill the boiler with deaerated feed water and maintain a slight pressure. When laying up a water-tube boiler wet, the goal is to prevent corrosion by keeping the entire internal surface submerged and isolated from air. Completely filling the boiler with deaerated (oxygen-free) feed water and maintaining a slight positive pressure achieves this, preventing air from entering the boiler and causing oxidation. The other options are incorrect because they either do not fully submerge the internal surfaces (draining and refilling) or do not maintain a protective pressure (simply filling to steam level).
Related Questions
Q@q.QuestionNumber:Which of the following statements represents the significance of the differentia... Q@q.QuestionNumber:In a boiler furnace, incomplete combustion due to insufficient air yields an exc... Q@q.QuestionNumber:Which of the conditions listed would indicate excessive soot buildup on the econ... Q@q.QuestionNumber:Which of the following represents the function of the diffuser used with a mecha... Q@q.QuestionNumber:Coast Guard Regulations
Ready to test your knowledge?
Take a Steam Plants - Assistant Engineer Practice ExamOfficial Resources
Want to practice with timed exams?
Download Coast Guard Exams for the full exam experience.
Get the App