70% to passOn U.S. inspected ships, oily-water separating equipment, bilge alarms, and bilge monitors must be approved under _______________.
A18 CFR 201
B33 CFR 151
C46 CFR 41
D46 CFR 162
AI Explanation
The correct answer is D) 46 CFR 162. 46 CFR 162 is the regulation that covers equipment requirements for U.S. inspected vessels, including oily-water separating equipment, bilge alarms, and bilge monitors. This regulation sets the standards and approval procedures for this type of equipment used on board inspected ships. The other options are incorrect because they do not specifically cover the equipment requirements for U.S. inspected vessels. 18 CFR 201 is related to general accounting and financial reporting, 33 CFR 151 covers pollution prevention regulations for vessels, but does not specifically address the approval of the equipment in question.
Related Questions
Q88:According to 33 CFR's, an oceangoing ship of over 400 gross tons must be fitted ... Q177:After measuring the length to which a section of shoring should be cut, you shou... Q27:Before entering any space that has been sealed, its oxygen level should be teste... Q91:The amount of garbage disposed must be entered into the records maintained by ea... Q160:Excessive free surface occurring in tanks carrying liquid cargo should be avoide...
Ready to test your knowledge?
Take a Safety & Environmental - Assistant Engineer Practice ExamOfficial Resources