Question 90Refrigeration & AC - Assistant Engineer
70% to passTo prevent the unnecessary loading of an air conditioning system while maintaining the designed dry bulb temperature and relative humidity in an air conditioning system, what should be done?
Aoperate the purge recovery unit continuously
Breduce the air reheating system load
Clower the compressor head pressure
Dadmit only enough fresh outside air to provide proper ventilation
AI Explanation
The correct answer is D) admit only enough fresh outside air to provide proper ventilation. Admitting only the necessary amount of fresh outside air is the best way to prevent the unnecessary loading of an air conditioning system while maintaining the desired dry bulb temperature and relative humidity. This approach ensures that the system is not overworked by introducing excessive outside air that requires additional cooling or dehumidification. The other options, such as continuously operating the purge recovery unit (A), reducing the air reheating system load (B), or lowering the compressor head pressure (C), are not as effective in optimizing the system's performance for the given conditions.
Related Questions
Q198:What is true concerning frost build-up on the evaporator coils of a multi-box di... Q144:What is the correct color-coding of refrigerant recovery cylinders regardless of... Q218:What is the purpose of the low-pressure cut-out switch as used as a primary cont... Q56:In a large refrigeration system having more than one evaporator, a king solenoid... Q153:Which of the fluids listed is suitable for use as a secondary refrigerant?
Ready to test your knowledge?
Take a Refrigeration & AC - Assistant Engineer Practice ExamOfficial Resources