Question 190Motor Plants - 1st Asst/Chief
70% to passCasing drains may be required on a waste heat boiler gas passage side to_______________.
Aprevent an accumulation of boiler water entering gas passages as a result of a pinhole tube leak
Bas a means to sample stack gases for testing
Crelease excess pressure
Ddrain off condensation
AI Explanation
The correct answer is D) drain off condensation. Casing drains on a waste heat boiler gas passage side are required to allow any condensation that forms in the gas passages to be drained off. This prevents the accumulation of water in the gas passages, which could potentially cause corrosion or other issues. The other answer choices are incorrect: A) is not the purpose of casing drains, B) refers to a different function, and C) is not the primary reason for casing drains on a waste heat boiler.
Related Questions
Q3:The lower water seal on a diesel engine wet cylinder liner must allow for liner ... Q96:The purpose of the interlocked three-way valve shown in the illustration is to _... Q224:The governor utilized with the device shown in the illustration has become inope... Q18:Bouncing of the valve gear in a diesel engine can be caused by_______________. Q227:If the input signal rises above the setpoint of '17A', shown in the illustration...
Ready to test your knowledge?
Take a Motor Plants - 1st Asst/Chief Practice ExamOfficial Resources