Question 301Electricity & Electronics - QMED
70% to passBefore working on an electric cargo winch master switch or controller, what should be done?
Aopen the circuit breaker in the power supply and tag-out
Bheat the switch box to remove any moisture
Cspray the gasket surface with a solvent
Ddrain condensate from the box
AI Explanation
The correct answer is A) open the circuit breaker in the power supply and tag-out. This is the correct answer because it is a critical safety procedure to de-energize the electrical system before working on any components. Opening the circuit breaker and tagging it out ensures that the system cannot be inadvertently energized while personnel are working on it, preventing the risk of electrical shock or other hazards. The other options are incorrect because they do not properly address the safety concerns. Heating the switch box, spraying the gasket with solvent, or draining condensate would not de-energize the system, and could potentially introduce other safety issues.
Related Questions
Q73:How is the power factor of an AC generator operating singularly determined? ... Q192:When paralleling two alternators using three synchronizing lamps, the flickering... Q427:In the circuit 'B' of the illustration, what would be the result of the upper he... Q41:Which of the electrical properties listed will always be the same across each co... Q167:Which of the listed statements is correct when using a digital multimeter set up...
Ready to test your knowledge?
Take a Electricity & Electronics - QMED Practice ExamOfficial Resources