Repair of vital machinery and services on a MODU should be accomplished _______________.

A after control of fire, but before control of flooding
B after control of fire, flooding, and structural repairs
C immediately
D after stability is restored
AI Explanation

The correct answer is B) after control of fire, flooding, and structural repairs. The reasoning behind this is that on a mobile offshore drilling unit (MODU), the priority in an emergency situation is to first control any fire, then control any flooding, and finally address any structural repairs. Only after these critical safety issues have been addressed should the focus shift to repairing vital machinery and services. This ensures the safety of the vessel and crew is the top priority before restoring full operational capability. The other options are incorrect because: A) repairing vital machinery should not be done before controlling flooding, as that could further compromise the vessel's stability and integrity; C) repairing vital machinery immediately may not be possible or advisable if other safety issues have not yet been resolved; and D) repairing vital machinery should not wait until stability is fully restored, as critical systems may need to be brought back online earlier in the emergency response process.

Ready to test your knowledge?

Take a Deck General Practice Exam

Want to practice with timed exams?

Download Coast Guard Exams for the full exam experience with progress tracking.

Get the App