Question 4747 Deck General
70% to passA virtual rise in the center of gravity of a MODU may be caused by _______________.
A
transferring pipe from the setback area to the pipe rack
B
filling a partially filled tank
C
emptying a partially filled tank
D
using an on board crane to lift a freely swinging heavy object
AI Explanation
The correct answer is D) using an on board crane to lift a freely swinging heavy object. The reason this is correct is that when a heavy object is lifted by a crane, the object's center of gravity rises, which in turn raises the overall center of gravity of the Mobile Offshore Drilling Unit (MODU). This change in the center of gravity can affect the MODU's stability and must be accounted for during operations. The other options are incorrect because transferring pipe (A) or filling/emptying a tank (B, C) would not directly affect the center of gravity in the same way as lifting a heavy object with a crane (D).
Related Questions
Q@q.QuestionNumber:The holding capacity of a mooring winch can be reduced by moisture on the break ...
Q@q.QuestionNumber:U.S. regulations require that cargo tanks in which grades B or C liquids are car...
Q@q.QuestionNumber:Most of your vessel's superstructure is forward. How will the vessel lie when dr...
Q@q.QuestionNumber:When instructing a crew member concerning the right way to lift a weight, you wo...
Q@q.QuestionNumber:A MODU with the TCG off the longitudinal centerline inclines to an angle of ___...
Ready to test your knowledge?
Take a Deck General Practice Exam
Official Resources
Want to practice with timed exams?
Download Coast Guard Exams for the full exam experience with progress tracking.
Get the App