Question 4462 Deck General
70% to passThe DEEP DRILLER is loaded as shown in Sample Load Form #4, (Drilling). In preparing for approaching heavy weather, the four leeward mooring lines are slacked. These actions reduce the _______________.
A
metacentric height
B
height of the righting arm
C
natural pitch period
D
righting moment
AI Explanation
The correct answer is C) natural pitch period. Slacking the leeward mooring lines reduces the righting moment acting on the vessel, which in turn increases the natural pitch period. This is because the reduced righting moment allows the vessel to pitch more freely, leading to a longer natural pitch period. The other options are incorrect because: A) Metacentric height is not directly affected by slacking the mooring lines. B) The height of the righting arm is also not directly affected by slacking the mooring lines. D) The righting moment is actually reduced by slacking the mooring lines, not increased.
Related Questions
Q4408:The DEEP DRILLER, at 60.0 feet draft in sea water, has VM = 974,441 foot-long to...
Q1434:Your tank vessel is fully loaded to the marks, and you find that she is down sli...
Q3444:You are on a semisubmersible being towed and are concerned that a fishing vessel...
Q944:While underway and towing an unmanned tank barge you are required to __________...
Q2941:Each person on the rig has a designated area to proceed to in the event of a fir...
Ready to test your knowledge?
Take a Deck General Practice Exam
Official Resources
Pass Your Coast Guard Licensing Exams!
Study offline, track your progress, and simulate real exams with the Coast Guard Exams app