Question 4342 Deck General

70% to pass

What port-side valves must be open to transfer ballast from Tank 1P to Tank 10P on the DEEP DRILLER using the Port #1 ballast pump?

A 1, 34, 35, and 23
B 1, 33, 44, 45, and 23
C 1, 33, 43, and 24
D 1, 33, 43, 48, and 23
AI Explanation

The correct answer is C) 1, 33, 43, and 24. To transfer ballast from Tank 1P to Tank 10P using the Port #1 ballast pump, the following port-side valves must be open: - Valve 1: Connects the Port #1 ballast pump to the ballast system - Valve 33: Allows flow from Tank 1P to the ballast manifold - Valve 43: Allows flow from the ballast manifold to Tank 10P - Valve 24: Allows the ballast to be discharged from Tank 10P The other answer choices are incorrect because they either include unnecessary valves or do not include all the required valves for this specific ballast transfer operation.

Ready to test your knowledge?

Take a Deck General Practice Exam

Want to practice with timed exams?

Download Coast Guard Exams for the full exam experience with progress tracking.

Get the App