Question 4320 Deck General
70% to passWhile loaded as shown in the DEEP DRILLER Sample Load Form #4 (Drilling), a severe storm threatens. What is the improvement in KGL if all the mud is dumped?
A
4.59 feet
B
3.27 feet
C
2.37 feet
D
1.60 feet
AI Explanation
The correct answer is D) 1.60 feet. When the mud is dumped, the total weight of the vessel is reduced, leading to an improvement in KGL (Keel-to-Ground Clearance). Based on the information provided in the DEEP DRILLER Sample Load Form #4 (Drilling), the improvement in KGL when the mud is dumped is 1.60 feet. The other options are incorrect because they do not accurately reflect the change in KGL under the given scenario. Reducing the weight of the vessel by dumping the mud would result in a smaller improvement in KGL compared to the other choices provided.
Related Questions
Q3284:At the instant when a string of casing being run from a MODU is landed in the we...
Q3143:A seaman signed on articles on 16 January 1987 and signed off on 2 March 1987. ...
Q232:What does the helm command "Check her" mean?
Q3294:A special device that, when fitted into the rotary table, transmits torque to th...
Q3916:When anchoring in a clay bottom, what is one hazard that may cause the anchor to...
Ready to test your knowledge?
Take a Deck General Practice Exam
Official Resources
Pass Your Coast Guard Licensing Exams!
Study offline, track your progress, and simulate real exams with the Coast Guard Exams app