Question 3763 Deck General
70% to passOn a MODU, each emergency generator must be tested at least once each _______________.
A
week
B
month
C
three months
D
six months
AI Explanation
The correct answer is B) month. The requirement for testing each emergency generator on a MODU (Mobile Offshore Drilling Unit) at least once each month is specified in the Code of Federal Regulations (CFR) Title 46, Section 111.15-5. This regulation states that each emergency generator must be tested under load for at least 2 hours at least once each month. The other options are incorrect because weekly testing (A) is not required, and testing every three (C) or six (D) months would not meet the regulatory requirement for monthly testing.
Related Questions
Q942:Which statement is TRUE of centrifugal pumps aboard tankers?
Q4985:The COASTAL DRILLER, with no list, is at a true mean draft of 10 feet and 10 inc...
Q4546:Most large anchors are manufactured with a _______________.
Q3996:You are mooring to a buoy. You should approach the buoy with the current from _...
Q2304:A vessel in ocean service that does not have an approved means of processing oil...
Ready to test your knowledge?
Take a Deck General Practice Exam
Official Resources
Pass Your Coast Guard Licensing Exams!
Study offline, track your progress, and simulate real exams with the Coast Guard Exams app