Question 1352 Deck General
70% to passWhat device will be activated while loading a LNG tank and the HI-HI liquid level set point is reached?
A
No shutdown required.
B
Overflow shutdown.
C
Remote shutdown valve control.
D
Emergency shutdown.
AI Explanation
The correct answer is D) Emergency shutdown. When the HI-HI liquid level set point is reached while loading an LNG (Liquefied Natural Gas) tank, an emergency shutdown (ESD) system will be activated. This is a critical safety feature required by regulations to prevent an overflow and potential hazardous situation. The ESD system will automatically shut down the loading process and close the appropriate valves to isolate the tank and stop the flow of LNG. The other options are incorrect because they do not adequately address the critical safety requirement to initiate an emergency shutdown in this scenario.
Related Questions
Q3434:The DEEP DRILLER is loaded as shown in the Sample Load Form #1 (Transit). Exces...
Q935:You have completed a crude oil wash. What action should be taken with the oil in...
Q1195:How many portable fire extinguishers are required in the cargo tank area of an u...
Q2889:You are the credentialed Master of a towing vessel operating between New York an...
Q1288:On what type of pump would you find an impeller?
Ready to test your knowledge?
Take a Deck General Practice Exam
Official Resources
Pass Your Coast Guard Licensing Exams!
Study offline, track your progress, and simulate real exams with the Coast Guard Exams app